The city of McAllen recently approved a conditional use permit for an AEP Texas electrical substation that officials say will make the local grid more reliable during storms as demand for electricity continues to grow.
The two-year permit is slated to expire in 2028 and is on city-owned property near Buddy Owens Boulevard and North Bentsen Road.
McAllen denied the company’s previous proposal for a permanent electrical substation after a nearby community pushed back in August 2025.
New plans include a temporary electrical substation on a platform on city owned land until AEP Texas secures its own property nearby. The temporary substation is still located near the subdivision where residents repeatedly advocated against the project.
A permanent substation is expected to be constructed along Buddy Owens, either near the intersection of Shary Road or Taylor Road, but the real estate deal is still under negotiation.
Joey Maldonado, from AEP Texas’ real estate division, told the commission that the company is finalizing a deal for a permanent site, which could sit within McAllen city limits or in the city of Palmhurst next door.
“We typically take about six months…to look at our due-diligence period — looking at title work to make sure the title is clear of any [liens] and then we also look at doing topography, geotech work, surveying, environmental. So we typically take about six months, and if need be, we can extend another six months,” Maldonado said.
AEP Texas did not respond to an interview request about the company’s plans for several more substations in McAllen.

Joaquin “JJ” Zamora, McAllen commissioner for District 2, initially voted against the project but changed his mind after the company hosted an informational community meeting in late March 2026.
“I also have to consider not just that neighborhood but the rest of everybody else that lives in that area,” Zamora said.
But that doesn’t mean the commission is keen on extending its temporary approval, Zamora said.
“Two years, and that has to be it. If you can expedite the process to have that permanent location, even better,” he said.
Daniel Lucio, the AEP Texas representative for the McAllen area, previously said it was critical to get the substation installed before the summer heat comes in — which can strain the grid with high demand.
“If we get to the summer season and we have extraordinary temperatures, servicing that area could be a concern,” Lucio said. “I appreciate the concerns from residents, but I want to make sure that come the heat of the summer, our residents are receiving the service they need from their electric supplier.”
AEP Texas serves 1.1 million customers, many of whom live in the Rio Grande Valley, but its service area also includes swaths of South, West, and East Texas. In 2024 alone, electricity demand from AEP Texas customers increased by 600 megawatts.
Most Read
- SpaceX is giving Brownsville $220M for water projects. In exchange, the city gave up zoning control of 444 acres near Starbase
- Port of Brownsville could soon host Nodule City, a first-of-its-kind commercial deep-sea mining hub
- What you need to know about Texas A&M’s newest manufacturing hub near the Port of Brownsville
- Harlingen hits pause on $27M offer from company planning 1,000-acre data center
- SpaceX seeks to take zoning control over nearly 450 acres from city of Brownsville as a ‘regional’ water deal takes shape
Get the latest business news delivered to your inbox every morning for free.
Try 30 Days Free!
Get full access to award-winning journalism covering business, real estate, health care, economic trends, and the people shaping the Rio Grande Valley.
30 Days Free!
$9.95/month
Limited time offer
Subscription renews after your 30 day free trial at $9.95/mo.
Included Benefits
- Unlimited access to all articles
- Daily business news and analysis
- Subscriber-only content and features
Stories That Matter
- Binational education leaders say they’re ready to train 10,000 for Port of Brownsville companies
- Valley Regional Medical Center plans $1.6M expansion
- McAllen produce distributor plans $8M cold storage warehouse
- Tamaulipas wants to put more of its products on Texas shelves
- Mission’s first Small Business Expo puts $25K on the line for local entrepreneurs
- Donna International Bridge upgrades tech ahead of commercial truck expansion as officials wait on Mexico
- Reynosa’s newest technical high school focuses on AI, semiconductors and bionics
- McCoy’s gives $10K, tools to launch Mid-Valley construction academy
- UT Health RGV performs new digestive procedure for first time in the Valley
- TSTC bets on advanced manufacturing to meet RGV’s industrial boom