The Anzalduas Bridge is two years behind on its commercial opening — but investors are already capitalizing on its potential
An aerial view of the Anzalduas International Bridge cargo inspection facilities as it prepares to open for commercial traffic, Sept. 5, 2025, in Mission, Texas. Courtesy of | Mission EDC | Jeremy Inglesi

While millions of passenger vehicles cross the Anzalduas International Bridge each year, the crossing still lacks its federal cargo inspection facility, now two years behind schedule and unlikely to open before spring 2026.

Teclo Garcia, the CEO of the Mission Economic Development Corporation (Mission EDC), said he recently learned of the latest delay in the commercial opening of the bridge’s cargo facilities.

Headshot of Teclo Garcia, the CEO of Mission EDC, in a grey suit with glasses.
Teclo Garcia

“The facilities are about 95 percent complete,” Garcia said. “(U.S. Customs and Border Protection) has specialized machinery and X-ray equipment they need to get here, and then get personnel trained on it, and that’s what’s taking up time.”

The future inspection facility is key to gaining profitable truck traffic.

Continue Reading

  • Unlimited news articles
  • Full access to all exclusive content

This article is available to subscribers only. Sign up to continue reading.


Daily Business Update

Get the latest business news delivered to your inbox every morning for free.

    Unlock Premium

    Support independent journalism.

    $9.95/month

    $1/week

    Limited time offer

    Enjoy Unlimited articals, exclusive newsletters, and deep insights.


    * Subscription renews December 31, 2025 at $9.95/mo.

    Subscribe Now

    U.S. slaps 25% tariff on heavy trucks, shaking Mexico’s $15B export industry

    October 19, 2025 • 3 min read

    Analysts warn the tariff could trigger higher transport costs and fresh uncertainty for manufacturers operating along the Texas–Mexico border.... Read more »

    Driscoll Children’s Hospital investing $2.2M in Edinburg expansions

    September 29, 2025 • 1 min read

    Projects will add more than 30,000 square feet of finished space at the Day Surgery at Renaissance facility.... Read more »