Second LNG export terminal at Port of Brownsville takes major step toward construction 
Rendering of storage tanks and processing facilities for the Texas LNG terminal. Courtesy of | Texas LNG

The company behind a second liquefied natural gas export terminal at the Port of Brownsville — a project estimated to cost $4 billion — told its general contractor on Friday to move forward with its plans. 

Texas LNG Brownsville LLC, a subsidiary of Houston-based Glenfarne Group LLC, announced that Kiewit Energy Group Inc., the contractor responsible for engineering, procurement and construction at the terminal has a ‘limited notice to proceed’ in July 2026. 

That means Kiewit expects to issue purchase orders for engineering activities, geotechnical work, and long- lead equipment, which is machinery, components, or systems that take a long time to manufacture, ship, or deliver after they’re ordered. 

The notice comes before the company makes a final investment decision — expected by the end of 2026. 

The decision, subsequent work, and purchase orders, “demonstrate the strength of the project’s world-class partner network and Glenfarne’s continued disciplined advancement of Texas LNG,” Brendan Duval, CEO of Glenfarne said in a news release. “By progressing key equipment, engineering and site readiness work, we are maintaining project momentum.” 

Texas LNG has a 50-year lease with the Port of Brownsville, a deal for 625 acres inked back in December 2020 for a 4 million tonnes per annum export terminal on the port channel. 

LNG terminal operators typically tap general contractors for the ground-up work. Betchel has been building the Rio Grande LNG terminal at the Port of Brownsville for Houston-based NextDecad, the port’s other LNG project already under construction.  

More than 6,000 workers have been working around the clock for Bechtel in Brownsville after the federal government recently allowed the project to employ night shifts to speed up construction. 

Similarly, Kiewit, the Omaha, Nebraska-based general contractor, would be in charge of hiring workers for the Texas LNG project. 

In mid-June, Kiewit posted job openings for an environmental project manager, a survey manager, and a grading superintendent in Brownsville, according to its website. 

Texas LNG projected it would support 975 jobs and produce $823 million in gross domestic product during the construction phase — which includes $40 million in sales taxes, $1.5 million in franchise tax fees, $12.3 million in other revenues to the state, and $3.1 million in sales taxes to nearby cities, according to its economic incentive application to the Point Isabel School District. 

Texas LNG promised the school district $15 million under the Texas Jobs, Energy, Technology, and Innovation, or JETI program, in addition to 110 high-paying permanent jobs. 

But the school board voted against approving the proposed incentives, worth $160 million.

Still, Cameron County leaders approved a 95% tax abatement for the company in 2024. 

Texas LNG has held its Federal Energy Regulatory Commission permit since November 2019. 

The company told federal regulators that Kiewit had already completed its front-end engineering and design work for the project, and that Texas LNG had begun its geoarchaeological survey and excavation work in May, according to Oscar Lopez, the Houston-based regulatory & permitting director for the company. 

LNG, or liquefied natural gas, is a compressed, supercooled product often exported overseas as an alternative energy source to nations without domestic energy extraction industries, such as many European and Asian countries. 

For example, Texas LNG has a long-term 20-year contract with German multinational energy company RWE Supply and Trading for 1 million tonnes of LNG annually — that’s about 25% of the export terminal’s capacity in Brownsville. 

Texas LNG also has a 20-year contract with the Australian multinational Macquarie Energy for 500,000 tonnes of LNG per annum. 

The company pitches itself as a greener export terminal because it plans to plug into the electric grid to power the facility instead of burning natural gas brought in by pipeline. 

The company said its facility will produce significantly lower carbon emissions than most LNG plants, which typically burn natural gas or steam to power refrigeration compressors — sometimes using up to 10% of incoming gas as fuel.

Because the South Texas grid includes wind and solar power, Texas LNG said it will not need carbon capture or offsets to meet its emissions goals.

Over the past few months, demand for LNG has pushed prices to record highs as a result of the military operations against Iran by the U.S. and Israel. The fight over access and control of the Strait of Hormuz in the Middle East has intermittently stalled vessel traffic in the ocean for months. 

The fighting halted LNG projection at the world’s largest facility in nearby Qatar after military weaponry damage. 

Peace talks among the U.S., Iran and Israel were on pause as of July 9, as the funeral for the slain Iranian leader Ali Khamenei, who was killed in war strikes by the U.S. and Israel in February, began Saturday.  

The price of LNG has cooled since a record high in March, when the war fighting began in earnest. In July, the natural gas market in Europe was still 60% higher than before the war began, but it was trading around 121% higher in mid-March 2026. 

Correction: The feature image originally published with this story did not depict the proposed Texas LNG facility.


Daily Business Update

Get the latest business news delivered to your inbox every morning for free.

    Try 30 Days Free!

    Get full access to award-winning journalism covering business, real estate, health care, economic trends, and the people shaping the Rio Grande Valley.

    30 Days Free!

    $9.95/month

    Limited time offer

    Subscription renews after your 30 day free trial at $9.95/mo.

    Included Benefits


    • Unlimited access to all articles
    • Daily business news and analysis
    • Subscriber-only content and features
    Get Full Access

    Data center developer pursuing Cameron County sues to block release of project records

    May 24, 2026 • 4 min read

    The dispute emerges as Harlingen puts a pause on data centers and Cameron County pushes for stronger oversight tied to... Read more »

    Starbase takes next step in massive expansion — here’s what you need to know

    March 18, 2026 • 4 min read

    As the process moves into the petition phase, debates intensify over access, jurisdiction, and future land use.... Read more »